Engineering company

Reference list

PJSC “ODESSA OIL REFINERY”

+
PERIOD, YEAR 2007-2008
PROJECT/OBJECT

Construction of “ELOU-AVT” unit )Electrical Desalting Plant – Crude Vacuum Distillation Unit)

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

EMERSON, Samson, Limitorq, Rosemount, Yokogawa, Wika, United Electric, Vega Swing, Fireye, Magnetrol, TopWorx, Drager, Pepperl+Fuchs, DeltaV, EMERSON

PERIOD, YEAR 2008
PROJECT/OBJECT

“Implementation of automated system for oil product filling into road tankers”

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

EMERSON Rosemount, Endres+Hauser, Drager, Pepperl+Fuchs, ПТКFloBoss, DeltaV, EMERSON

PERIOD, YEAR 2008-2009
PROJECT/OBJECT

Construction of acid tar visbreaking unit

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

EmersonDeltaV Samson, Camozzi, Yokogawa, Wika, United Electric, Vega Swing, Fireye, Magnetrol, TopWorx, Drager, Pepperl&Fuchs, Rosemount

PERIOD, YEAR 2008-2009
PROJECT/OBJECT

Construction of a nitrogen unit

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

ПТКSimatic, Siemens, Sfaif, Siemens, Pepperl+Fuchs, EMERSON

PERIOD, YEAR 2008-2009
PROJECT/OBJECT

“Implementation of the control system in workshop UPHG & FS” (Gas underground storage & gusher wells)

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

EmersonDeltaV Samson, Yokogawa, Wika,Magnetrol, Drager, Pepperl&Fuchs, Rosemount

PERIOD, YEAR 2008-2009
PROJECT/OBJECT

“Implementation of the vibromonitoring system of compressor ЦК-1”

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission

PRODUCERS OF EQUIPMENT USED

EmersonDeltaV Samson, Yokogawa, Wika,Magnetrol, Drager, Pepperl&Fuchs, Rosemount

PERIOD, YEAR 2008-2009
PROJECT/OBJECT

“Implementation of the control system of UVPB unit” (gasoline rerun unit)

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

EMERSON, Samson, Rosemount, Yokogawa, Wika, Magnetrol, Drager, Pepperl+Fuchs

PERIOD, YEAR 2009
PROJECT/OBJECT

“Implementation of the modernized control of processes of the ELOU-AVT” unit”

DESCRIPTION OF WORKS/SERVICE

Design and survey works Engineering works Commissioning works

DIRECTION

APCS Telecommunication and data transmission

PRODUCERS OF EQUIPMENT USED

Honeywell I&C complex ProfitSuite

PERIOD, YEAR 2009
PROJECT/OBJECT

“Implementation of the engineering and manufacturing collection & storage system”

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Engineering works Commissioning works

DIRECTION

APCS Telecommunication and data transmission

PRODUCERS OF EQUIPMENT USED

Honeywell I&C complex Uniformance R200

PERIOD, YEAR 2009-2010
PROJECT/OBJECT

“Construction of KGO ( gasoline hydrotreater) unit, replacement of the existing APCS, type RS-3, by Delta-V, configuring and adjusting of instrumentation of the kerosene cut unit”

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

EMERSON, Samson, Rosemount, Yokogawa, Krohne, Wika, United Electric, Vega Swing, Fireye, Magnetrol, TopWorx, Drager, Pepperl+Fuchs, DeltaV

PERIOD, YEAR 2009-2010
PROJECT/OBJECT

Installation of the recycling and fire water pumping station in the VIK (water supply & sewerage) shop

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

Limitorq Rosemount, Yokogawa, Drager, Foxboro

PERIOD, YEAR 2010
PROJECT/OBJECT

“Installation of the control system in the TSTS shop (crude gasoline shop)”

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

DeltaV, EMERSON, Samson, LimitorqRosemount, Yokogawa, Enraf, Drager, Wika

PERIOD, YEAR 2010
PROJECT/OBJECT

“Implementation of the production and technological data visualization system”

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

APCS Telecommunication and data transmission

PRODUCERS OF EQUIPMENT USED

Honeywell I&C complex, BusinesFlex

PERIOD, YEAR 2010-2011
PROJECT/OBJECT

“Implementation of a comprehensive environmental monitoring system“

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Energy supply

PRODUCERS OF EQUIPMENT USED

Vaisala, “Delta-C, Ltd.”, CJSC “OPTEC”, NIKI-MLT, Ltd.” – Volga region

PERIOD, YEAR 2012-2013
PROJECT/OBJECT

Implementation of a local early warning and alert system

DESCRIPTION OF WORKS/SERVICE

Design and survey works Supply of equipment and materials Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmissionn Energy supply

PRODUCERS OF EQUIPMENT USED

ПТКDeltaV, EMERSON, Honeywell, Drager, LA CROSSE

PERIOD, YEAR 2013-2017
DESCRIPTION OF WORKS/SERVICE

Maintenance Running repairs Off-scheduled repairs Equipment adjustment

DIRECTION

Instrumentation APCS Telecommunication and data transmission Fire alarm & fire extinguishment

PERIOD, YEAR 2013-2017
DESCRIPTION OF WORKS/SERVICE

Servicing on informative & processing support of business projects

DIRECTION

Computing office equipment Local information systems Information Support Information Security Ensuring the functioning of equipment and systems used in business processes

PERIOD, YEAR 2013-2017
DESCRIPTION OF WORKS/SERVICE

Works on metrological support in attesting – calibration of instrumentation

DIRECTION

Instrumentation APCS

Karpatneftkhim, Ltd.

+
PERIOD, YEAR 2010-2013
PROJECT/OBJECT

Reconstruction of APCS of the ethylene plant

DESCRIPTION OF WORKS/SERVICE

Design and survey works Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Fire alarm and extinguishment Climatic systems

PRODUCERS OF EQUIPMENT USED

Yokogawa I&C complex, Centum VP~4500 парам; ICC ProSafe RS~2500 парам., Samson,Norgren, Emerson, Pfannenberg

FICE “LUCOIL – Ukraine”

+
PERIOD, YEAR 2007-2008
PROJECT/OBJECT

Reconstruction of oil product storage base” – town of Boryspol

DESCRIPTION OF WORKS/SERVICE

Design and survey works Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Power supply

PRODUCERS OF EQUIPMENT USED

Allen-BradleyI&C complex ControlLogix I&C complex «Petronix», Enraf, Dräger

PERIOD, YEAR 2010-2013
PROJECT/OBJECT

Reconstruction of oil product storage base” – town of Kremenets

DESCRIPTION OF WORKS/SERVICE

Design and survey works Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Power supply Fire alarm and extinguishing

PRODUCERS OF EQUIPMENT USED

Allen-Bradley I&C complex ControlLogix I&C complex «Petronix», Enraf, Dräger

PERIOD, YEAR 2011-2014
PROJECT/OBJECT

Gasoline filling stations – 278 pcs.

DESCRIPTION OF WORKS/SERVICE

Maintenance Running repairs Out-scheduled repair Servicing in the IT support of business-processes Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Computer office equipment Information support Information safety Servicing equipment and systems used in business-processes

PRODUCERS OF EQUIPMENT USED

I&C complex “Petronix” УУС-01, УУС-01М, PetroVend, APC

PERIOD, YEAR 2011-2012
PROJECT/OBJECT

Gasoline displacement unit “EKTO” City of Dnepropetrovsk

DESCRIPTION OF WORKS/SERVICE

Design and survey works Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Power supply

PRODUCERS OF EQUIPMENT USED

I&C complex “Petronix” Honeywell-Enraf

PERIOD, YEAR 2012-2013
PROJECT/OBJECT

Diezel fuel accounting unit” Town of Kremenets

DESCRIPTION OF WORKS/SERVICE

Design and survey works Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Power supply

PRODUCERS OF EQUIPMENT USED

I&C complex “Petronix” Yokogawa

PERIOD, YEAR 2012-2013
PROJECT/OBJECT

Reconstruction of the oil product storage base:” Town of Borodyanka

DESCRIPTION OF WORKS/SERVICE

Design and survey works Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Power supply Fire alarm and extinguishing

PRODUCERS OF EQUIPMENT USED

Allen-Bradley I&C complexControlLogix I&C complex «Petronix», Enraf, Dräger

PERIOD, YEAR 2012
PROJECT/OBJECT

Gasoline displacement unit “EKTO” City of Symferopol

DESCRIPTION OF WORKS/SERVICE

Design and survey works Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Telecommunication and data transmission Power supply

PRODUCERS OF EQUIPMENT USED

I&C complex «Petronix», Honeywell -Enraf

PJSC “Azot” (Nitrogen)

+
PERIOD, YEAR 2013
PROJECT/OBJECT

“Reconstruction of the natural gas commercial accounting unit on the base of DCF “Centum CS” of the “Yokogawa “ company

DESCRIPTION OF WORKS/SERVICE

Design and survey works Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

APCS Telecommunication and data transmission

PRODUCERS OF EQUIPMENT USED

ПТК CentumVP, Yokogawa(~100 парам.),HP, DELL

PJSC “MIRONOVSKYI FACTORY FOR CEREAL & FEED-STUFFS PRODUCTION

+
PERIOD, YEAR 2015
PROJECT/OBJECT

Electro-engineering installation of the heat generating plant

DESCRIPTION OF WORKS/SERVICE

Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation Power supply

OLYMPEX COUPE INTERNATIONAL, LTD

+
PERIOD, YEAR 2016
PROJECT/OBJECT

Repair. Mechanization section on repair and service of fire and gas detection system. Electric and engineering part”

DESCRIPTION OF WORKS/SERVICE

Equipment and materials supply Cable and wire product supply

DIRECTION

Relay protection and automatics

PRODUCERS OF EQUIPMENT USED

Electrum, Intercabel Kyiv Eaton

PERIOD, YEAR 2016
PROJECT/OBJECT

Repair. Mechanization section on repair and service of fire and gas detection system. Electric and engineering part”

DESCRIPTION OF WORKS/SERVICE

Installation works

DIRECTION

Relay protection and automatics

PRODUCERS OF EQUIPMENT USED

DKC,Eaton

PJSC “LINIK”

+
PERIOD, YEAR 2016-2017
DESCRIPTION OF WORKS/SERVICE

Equipment and materials supply

DIRECTION

Relay protection and automatics

PRODUCERS OF EQUIPMENT USED

EATON, SIEMENS, PANASINIC, M-EPCOS

DTEC “ELECTRONALADKA (Electric adjustment), Ltd.”

+
PERIOD, YEAR 2017
PROJECT/OBJECT

Implementation of the control station system for power unit of st. No. 3 DTEC ZAPOROZHSKA THERMAL ELECTRIC POWER STATION

DESCRIPTION OF WORKS/SERVICE

Construction and installation works Commissioning works

DIRECTION

Instrumentation APCS Computer office equipment Information support Telecommunication and data transmission

PERIOD, YEAR 2017-2018
PROJECT/OBJECT

DTEC BURSHTYNSKA THERMAL ELECTRIC POWER STATION

DESCRIPTION OF WORKS/SERVICE

Construction and installation works Commissioning works

DIRECTION

APCS Computer office equipment Information support

PJSC “UkrGazdobycha”

+
PERIOD, YEAR 2016
PROJECT/OBJECT

“Shebelinsky dept. of gas condensate and oil processing (VPGKN) Construction of diesel fuel hydrotreating unit with yield of 150 th. tons a year. Commissioning works in the control system”.

DESCRIPTION OF WORKS/SERVICE

Design and survey work Construction and installation works Engineering works Commissioning works

DIRECTION

APCS

PRODUCERS OF EQUIPMENT USED

Emerson, Dell

PERIOD, YEAR 2016
PROJECT/OBJECT

“Shebelinsky dept. of gas condensate and oil processing (VPGKN). Modernization of the control system Delta V”.

DESCRIPTION OF WORKS/SERVICE

Check for conformity of the design docs to the works carried out. Engineering works Commissioning works

DIRECTION

Instrumentation APCS Computer office equipment Information support

PERIOD, YEAR 2017
PROJECT/OBJECT

Construction of facilities of Yablunivsky gas condensate field. Technical re-equipment of the automated control system of the technological process of the complex GTU Yablonovka. Commissioning works.

DESCRIPTION OF WORKS/SERVICE

Check for conformity of the design docs to the works carried out. Engineering works Commissioning works

DIRECTION

Instrumentation APCS Computer office equipment Information support

PERIOD, YEAR 2017
PROJECT/OBJECT

Construction of facilities of Solokhovsky gas condensate field. Technical re-equipment of the automated control system of the technological process of the complex GTU Solokhovka. Design and survey work

DESCRIPTION OF WORKS/SERVICE

Design and survey work

DIRECTION

Instrumentation APCS Computer office equipment

PERIOD, YEAR 2018
PROJECT/OBJECT

Condensate stabilization process shop. Reconstruction of APCS of condensate stabilization unit and battery

DESCRIPTION OF WORKS/SERVICE

Design and survey works

DIRECTION

APCS Instrumentation Building part

PRODUCERS OF EQUIPMENT USED

Eaton, Lapp, Rittal, , Phoenix-Contact, Siemens, Odeskabel, DKC, Dell, Moxa

PERIOD, YEAR 2018
PROJECT/OBJECT

Shebelinsky dept. of gas condensate and oil processing (VPGKN). Modernization of the motor benzene and diesel fuel mixing unit with installation of flow analyzers. Project works.

DESCRIPTION OF WORKS/SERVICE

Design and survey works

DIRECTION

APCS Instrumentation

PRODUCERS OF EQUIPMENT USED

Emerson, , Phoenix-Contact, Rittal, Schneider Electric, DKC, Odeskabel, APC, Moxa, Optokon, Hewlett Packard, ATEN

PERIOD, YEAR 2018
PROJECT/OBJECT

Shebelinsky dept. of gas condensate and oil processing (VPGKN). Dispatching of material flows of processing units for making up gas balance

DESCRIPTION OF WORKS/SERVICE

Design and survey works

DIRECTION

APCS Instrumentation

PRODUCERS OF EQUIPMENT USED

MTL Instruments, Emerson, A-TEKC, Phoenix-Contact, Rittal, Schneider Electric, DKC, Odeskabel, APC, Moxa, Optokon, Hewlett Packard, ATEN

PERIOD, YEAR 2018
PROJECT/OBJECT

Shebelinsky dept. of gas condensate and oil processing (VPGKN). Reconstruction of automated oil product release system of the bulkhead of the road tanker. Survey works

DESCRIPTION OF WORKS/SERVICE

Design and survey works

DIRECTION

APCS Instrumentation Building part

“Concern Galnaftogaz”

+
PERIOD, YEAR 2016-2017
PROJECT/OBJECT

Technical service and repair of the level measurement systems at the FFS :”OCCO” (270 pcs)

DESCRIPTION OF WORKS/SERVICE

Technical service Running repair Out-scheduled repair Equipment and materials supply Construction and installation works Engineering works Commissioning works

DIRECTION

Instrumentation APCS Computer office equipment Information support Information safety

PRODUCERS OF EQUIPMENT USED

УУС-01, УУС-01М, Petro Vend, APC

ELECTRIC MOUNTING SERVICE, Ltd

+
PERIOD, YEAR 2017
PROJECT/OBJECT

“Automation of silicate autoclave unloading” at the object of “Procter & Gamble Manufacturing – Ukraine, Ltd.”

DESCRIPTION OF WORKS/SERVICE

Design and survey work Engineering works Commissioning works

DIRECTION

APCS Instrumentation

PRODUCERS OF EQUIPMENT USED

Allen-Bradley

S-Engineering, Ltd.

+
PERIOD, YEAR 2017
PROJECT/OBJECT

Reconstruction of the processing line No. 1 within the Project “Railside terminal of raw applications/ Building for dosing application unit with galleries”

DESCRIPTION OF WORKS/SERVICE

Installation works

DIRECTION

APCS Telecommunication and data transmission

PERIOD, YEAR 2017
PROJECT/OBJECT

Reconstruction of the processing line No. 1 within the Project “Railside terminal of raw applications/ Building for dosing application unit with galleries”

DESCRIPTION OF WORKS/SERVICE

Installation works

DIRECTION

Grounding systems Relay protection and automatics

PJSC “VEGA PLUS”

+
PERIOD, YEAR 2017
DESCRIPTION OF WORKS/SERVICE

Equipment and materials supply

DIRECTION

Instrumentation

PRODUCERS OF EQUIPMENT USED

Yokogawa

Фото: Каска OGCS

ROSTOK, Ltd

+
PERIOD, YEAR 2017
PROJECT/OBJECT

Design docs for construction object “Automated system of duel discharge to road-tankers at the excise warehouse of combustibles and lubricants”

DESCRIPTION OF WORKS/SERVICE

Design and survey works

DIRECTION

APCS Instrumentation, Processing equipment

PRODUCERS OF EQUIPMENT USED

Yokogawa

“Panda, Ltd.” company

+
PERIOD, YEAR 2017
DESCRIPTION OF WORKS/SERVICE

Equipment and materials supply

DIRECTION

Instrumentation

PRODUCERS OF EQUIPMENT USED

Yokogawa

Фото: Каска OGCS

PrJSC “Oil, gas production”

+
PERIOD, YEAR 2017-2018
PROJECT/OBJECT

Construction of facilities of. Autonomous system for controlling well No. 25 operation

DESCRIPTION OF WORKS/SERVICE

Equipment and materials supply

DIRECTION

Instrumentation APCS Telecommunication and data transmission

PRODUCERS OF EQUIPMENT USED

AGRO, Cisco, EATON, Emerson, CONTA-CLIP, Phoenix Contact, Yokogawa, Radiolex, Schroff, Premium line, Тера , DKC, Axis, Optex, DSSL

PERIOD, YEAR 2018
PROJECT/OBJECT

Automated system of emergency early alarm and people notification at the Semirenkovo gas condensate field. The site for finished product storage. Condensate filling unit.

DESCRIPTION OF WORKS/SERVICE

Equipment and materials supply, Engineering works

DIRECTION

APCS Instrumentation

PRODUCERS OF EQUIPMENT USED

Siemens

PERIOD, YEAR 2018
PROJECT/OBJECT

Automated system of supervisory control. Reconstructions

DESCRIPTION OF WORKS/SERVICE

Design and survey works Construction and installation works Engineering works Commissioning works Equipment and materials supply

DIRECTION

APCS Instrumentation, Computer office equipment, Information support

PERIOD, YEAR In the process of execution. Dead time - 2019
PROJECT/OBJECT

Construction of facilities at the Semirenkovo gas condensate field. Autonomous system of controlling well No. 43 operation. New construction

DESCRIPTION OF WORKS/SERVICE

Construction and installation works, Engineering works, Commissioning works, Equipment and materials supply

DIRECTION

APCS, Instrumentation, Computer office equipment, Information support

Фото: Каска OGCS

PE “CORDA PLUS”

+
PERIOD, YEAR 2017
DESCRIPTION OF WORKS/SERVICE

Equipment and materials supply

DIRECTION

Instrumentation

PRODUCERS OF EQUIPMENT USED

Yokogawa

Yokogawa Electric – Ukraine, Ltd.

+
PERIOD, YEAR 2014-2015
PROJECT/OBJECT

Reconstruction of the ammonia production unit AM-600 “RUSTAVELY AZOT”

DESCRIPTION OF WORKS/SERVICE

Survey Data collection, Design and survey works

DIRECTION

Instrumentation, APCS

PERIOD, YEAR 2015
PROJECT/OBJECT

APCS migration on the Yokogawa I&C complex with “Centum CS3000” on “Centum of “Sudzuker – Moldova” joint venture

DESCRIPTION OF WORKS/SERVICE

Survey, Data collection, Design and survey works

DIRECTION

APCS

PERIOD, YEAR 2015
PROJECT/OBJECT

Automated monitoring, control and safety system of air (oxygen) separation products system in the oxygen shop of PJSC “Ilyich MMK”

DESCRIPTION OF WORKS/SERVICE

Survey, Data collection, Design and survey works

DIRECTION

APCS

PERIOD, YEAR 2017
DESCRIPTION OF WORKS/SERVICE

Equipment supply

DIRECTION

Instrumentation, APCS

PJSC “ODESSA PORT PLANT”

+
PERIOD, YEAR 2015-2017
DESCRIPTION OF WORKS/SERVICE

Equipment and materials supply

DIRECTION

Instrumentation, APCS, Repay protection and automatics

PRODUCERS OF EQUIPMENT USED

Druck, WIKA, YOKOGAWA, PARKER, MTL, ДКС, PHOENIX CONTACT, Weidmuller, Kopos, RITTAL, WAGO, PHOENIX CONTACT, RITTAL, EATON, SNEIDER ELECTRIC, ELHAND


Get a technical solution

The automation of production processes begins when a task that determines the automation level is being set ...

Learn more
фоновое изображение

Задать вопрос

Связаться с нами

Ask a Question

Получить техническое решение